The argument
The tape · quarterly coverage amplitude · live quarter blinking
Applied Digital (APLD, Nasdaq) does not sell chips and does not rent GPUs by the hour. It builds data-center buildings in North Dakota and Texas, secures the megawatts to run them, and leases both to whoever needs compute at scale. Its largest tenant, by a wide margin, is CoreWeave — the same Nvidia-backed neocloud whose own report on this site tracks the demand side of the AI capex cycle. Applied Digital is the supply side: the landlord, not the renter.
It did not start there. The company was Applied Blockchain, Inc. when it uplisted to the Nasdaq at $5 a share in April 2022, a hosting provider for bitcoin-mining rigs. It renamed itself Applied Digital Corporation that November, keeping the ticker, and started describing the same buildings and the same power contracts as infrastructure for “high-performance computing.” The market did not buy the rebrand right away. Short seller Wolfpack Research called the pivot “an embarrassing and predictable stock promotion” in July 2023, labeling the company “a potato farm turned failed bitcoin miner” and flagging that insiders at investment bank B. Riley Financial held a stake near 48%. The stock fell double digits on the report. Applied Digital disputed it and kept building. What follows is the record of what the buildings turned into — and how thin outside coverage of that turn still is, which is exactly the gap a frontier-tier report exists to close.
TEXXR’s corpus first tags the company in September 2024, when Nvidia and other investors put $160 million into Applied Digital to fund its data-center and AI-cloud buildout — a chip supplier underwriting the power layer beneath it, months before the CoreWeave relationship existed on paper. Four months later, Applied Digital agreed to a financing partnership with Macquarie Asset Management worth up to $5 billion, aimed at funding its Ellendale, North Dakota campus without diluting equity. The capital arrived before the tenants did: Applied Digital’s fiscal Q3 2025 results, reported that April, missed revenue estimates as existing clients delayed renewing their leases, and the stock fell 36% the next session; the same week, CoinDesk reported the company was also moving to sell off its lower-margin cloud-computing unit — the first public sign Applied Digital was narrowing itself to the landlord business alone.
Then the CoreWeave leases arrived, and the narrative inverted. Applied Digital announced two 15-year leases with CoreWeave in June 2025 for 250 megawatts at its Ellendale campus, worth an estimated $7 billion in total revenue, and its stock jumped 48% in a single session. CoreWeave exercised an option for another 150 megawatts that August, pushing the campus to 400 megawatts and the contracted total to roughly $11 billion. By October, Applied Digital had closed the first tranche of the Macquarie facility, posted a quarter strong enough to send shares up another 16%, and signed a third lease — $5 billion, 200 megawatts, 15 years — with an unnamed U.S.-based, investment-grade hyperscaler at a second campus near Harwood, North Dakota. That customer’s identity has never been disclosed in any source found for this report; the record simply doesn’t say, which is itself worth flagging rather than guessing past. Combined, the CoreWeave and hyperscaler leases then ran to roughly $16 billion in contracted revenue across 600 megawatts, and the first 50-megawatt phase went live in late October 2025. By May 2026, leases at a third North Dakota campus and two southern ones had lifted the total to about $36 billion across 1,410 megawatts, per the company’s annual report.
Nvidia’s own position tells a sharper story than the leases do. Having seeded the pivot in 2024, Nvidia’s 13F filing revealed in February 2026 that it had sold its entire Applied Digital stake — all 7.7 million shares, valued at $177 million three months earlier — even as CoreWeave’s footprint on Applied Digital’s own land kept expanding. Nvidia backed the landlord early, then rotated the money toward the tenant instead. A month later, the relationship deepened in a different register: CoreWeave moved its two original Ellendale leases, in whole or part, into a dedicated subsidiary, backed them with a springing parent guarantee and a $50 million letter of credit, and pointed to higher ratings on its refinanced debt for those sites; Applied Digital judged the change favorable to holders of its 9.25% notes. Fiscal Q3 2026 revenue, reported that April, came in at $126.6 million, up 139% year over year, though a $59.7 million write-down of the cloud unit, taken when it stopped being held for sale, widened the GAAP net loss to $100.9 million. In June 2026, Montana-Dakota Utilities agreed to supply power to Polaris Forge 3, a third North Dakota campus near Center — the same utility that already powers Ellendale. That campus had been leased on May 20 to an unnamed investment-grade hyperscaler.
The spectrogram
Signal decomposition · what the record is made of, by quarter · brightness = share of edges · drift = how far the story moved in meaning
In 2024Q3 the record was 100% financial; by 2025Q2 it is 100% financial. A price chart shows what a name did; the spectrogram shows what its story is made of.
The brains
Grid interconnection secured ahead of tenants at three straight campuses — a real Cornered Resource pattern, entangled with a tenant's own credit.
Sixteen billion dollars in contracted leases and two articles in the record built to check them against.
Credit that runs through one tenant's guarantee, funding conversion capex against two years of disclosed record.
The machine
TEXXR’s corpus carries exactly two articles tagged to Applied Digital across its full history: the September 2024 Nvidia investment and the April 2025 earnings miss. That’s the whole footprint — one article in 2024 Q3, one in 2025 Q2, and nothing since, per TEXXR’s own momentum tracking. All four extracted edges classify as financial, a 100% single-predicate profile. Querying the graph for edges connecting Applied Digital to CoreWeave directly returns zero — despite $11 billion in contracted lease revenue between them being the defining fact of both companies’ current existence. See CoreWeave’s own report for the contrast: 294 edges touch that name alone, as of October 27. The corpus that catches Meta’s $21 billion CoreWeave commitment same-day misses the landlord underneath CoreWeave’s own buildings entirely. That gap is not a flaw to route around — it’s the frontier-tier thesis in miniature: the news system covers the compute buyer, not the ground it stands on.
The money
Currency: USD. Revenue/net income/capex/FCF cross-checked against filed XBRL.
Positioning: how much of APLD is sold short, on the record brokers file twice a month. It lags by design — read it as where the crowd stood, not where it stands.
The record
- Tenant concentration. CoreWeave’s leases are about $11 billion of the roughly $36 billion contracted; the company says about 70% is now backed by investment-grade hyperscalers it does not name — a split to hold against future lease disclosures.
- ChronoScale. The cloud unit was not sold. On May 5, 2026 it became ChronoScale, a Nasdaq-listed company Applied Digital owns about 97% of — the clearest signal of whether Applied Digital becomes a pure landlord or keeps a compute business alongside it.
- Polaris Forge 2’s hyperscaler. The $5 billion tenant behind the October 2025 lease has never been named in any source reviewed for this report, nor have the tenants of the three campuses leased since. Whether that identity surfaces in a future 10-K or stays unconfirmed is its own signal about how these deals get disclosed.
- The credit-support template. The March 2026 move of two Ellendale leases into a CoreWeave subsidiary with a parent guarantee is a structure — tenant credit enhancing landlord debt — that a June 2026 memorandum would repeat for a third lease, ELN-04, if that subsidiary wins an investment-grade rating.
- Short interest against the backlog. Roughly 27% of Applied Digital’s float was reported sold short in July 2026, a level that sits uneasily next to about $36 billion of contracted revenue — the kind of split the record doesn’t resolve on its own.
- Polaris Forge 2’s first power. The company expects initial operations at Harwood to lift delivered load across its North Dakota campuses to 300 megawatts by the end of calendar 2026 — a dated test of leases turning into buildings.
| Quarter | Articles | QoQ | Q-end price | QoQ | The record reads |
|---|---|---|---|---|---|
| 2024Q3 | 1 | — | 8.25 USD | — | first quarter on record |
| 2025Q2 | 1 | +0% | 10.07 USD | +22.1% | price rose, attention steady |
The peers
Applied Digital lives or dies by the same constraint as these names — small equal-weighted groups, one constraint each. Not investment products: see all categories.
Renting the compute out again — the capital constraint, 1.5 independent bets across 5 names
The rigs that became data centres — the siting constraint, 1.5 independent bets across 11 names
Sources
Verified externally (not in TEXXR’s corpus as of this writing):
- Applied Blockchain, Inc. name-change and April 2022 Nasdaq uplisting at $5/share — Applied Digital investor relations and Renaissance Capital, 2022. https://ir.applieddigital.com/news-events/press-releases/detail/44/applied-blockchain-announces-official-name-change-to · https://www.renaissancecapital.com/IPO-Center/News/92017/Applied-Blockchain-prices-Nasdaq-uplisting-at-$5-below-the-downwardly-revis
- Wolfpack Research short report and market reaction — MarketScreener, 2023-07-06. https://www.marketscreener.com/quote/stock/APPLIED-DIGITAL-CORPORATI-120787468/news/Applied-Digital-Stock-Falls-14-After-Wolfpack-Research-Short-Report-44281743/
- Macquarie Asset Management partnership announcement (up to $5B) — Macquarie Group, 2025-01-14. https://www.macquarie.com/us/en/about/news/2025/macquarie-asset-management-agrees-to-form-a-partnership-with-applied-digital.html
- CoinDesk report on planned cloud-unit sale — CoinDesk, 2025-04-15. https://www.coindesk.com/markets/2025/04/15/applied-digital-tumbles-30-on-revenue-miss-plans-sale-of-cloud-computing-unit
- CoreWeave $7B, 250MW lease agreement and 48% stock jump — CNBC, 2025-06-02. https://www.cnbc.com/2025/06/02/applied-digital-coreweave-ai.html
- Additional 150MW CoreWeave lease, bringing total to $11B/400MW — Capacity Media, 2025-08-29. https://capacityglobal.com/news/applied-digital-coreweave-data-centre-lease/
- Macquarie closes first investment tranche — Macquarie Group, 2025-10-07. https://www.macquarie.com/at/en/about/news/2025/mam-closes-first-investment-in-partnership-with-applied-digital-providing-up-to-us5billion-in-funding-to-support-high-performance-computing-growth.html
- Q1 FY2026 earnings, stock +16% — CNBC, 2025-10-10. https://www.cnbc.com/2025/10/10/applied-digital-stock-ai-data-center-earnings.html
- $5B, 200MW lease with unnamed U.S. hyperscaler at Polaris Forge 2 — CNBC, 2025-10-22. https://www.cnbc.com/2025/10/22/applied-digital-signs-5-billion-ai-factory-lease-with-us-based-hyperscaler.html
- First 50MW phase ready for service, Ellendale — DataCenterDynamics, 2025-10-27. https://www.datacenterdynamics.com/en/news/first-50mw-ready-for-service-at-applied-digital-data-center-in-ellendale-north-dakota/
- Nvidia’s full exit of its Applied Digital stake, per 13F filing — Investing.com, 2026-02-20. https://www.investing.com/news/stock-market-news/applied-digital-stock-falls-after-nvidia-drops-stake-93CH-4509888
- CoreWeave lease restructuring at Ellendale and A3 investment-grade credit rating — TheEnergyMag, 2026-03-31. https://www.theenergymag.com/news/market-news/applied-digital-modifies-ellendale-data-center-leases-following-coreweave-credit-upgrade
- Fiscal Q3 2026 earnings results and transcript — The Motley Fool, 2026-04-09. https://www.fool.com/earnings/call-transcripts/2026/04/09/applied-digital-apld-q3-2026-earnings-transcript/
- Montana-Dakota Utilities electric service agreement for Polaris Forge 3 (430MW) — Daily Energy Insider, 2026-06. https://dailyenergyinsider.com/news/52776-montana-dakota-utilities-to-provide-power-for-applied-digitals-data-center-campus/
- Delta Forge 2 lease and the ~$36B five-campus portfolio, ~70% backed by investment-grade hyperscalers — Applied Digital press release, 2026-06-08 (SEC 8-K, 2026-06-09).
- Lease table (1,410 MW, ~$36.2B; Polaris Forge 3 lease of 2026-05-20) — Applied Digital annual report on Form 10-K, filed 2026-07-29, SEC EDGAR.
- CoreWeave lease amendment, springing guaranty and $50M letter of credit — Applied Digital 8-K/A, 2026-04-01; cloud unit write-down — fiscal Q3 2026 results release, 2026-04-08; ChronoScale closing — 8-K, 2026-05-05; ELN-04 memorandum — 8-K, 2026-06-09; Polaris Forge 2 timing — fiscal Q1 2027 results release, 2026-10-07. SEC EDGAR.
- Nvidia 13F-HR filings for 2025-09-30 (7,716,050 APLD shares, $177.0M) and 2025-12-31 (none, filed 2026-02-17) — SEC EDGAR.
- Stock moves (2025-04-15, 2025-06-02, 2025-10-10) — our archive of as-traded closes.
- Short interest data (~27% of float) — MarketBeat, accessed 2026-07. https://www.marketbeat.com/stocks/NASDAQ/APLD/short-interest/
- Ticker/exchange verification: Applied Digital Corporation (APLD, Nasdaq) — verified against Yahoo Finance and stockanalysis.com, July 2026.
Edges (TEXXR knowledge graph): 68393, 68394, 68395, 50004. Edges-between query, CoreWeave and Applied Digital: 0 (requeried 2026-10-27).